Message ID | 13/09/2022, version 2 |
Type of unavailability | Unplanned |
Type of event | Failure |
Event Start | 13/09/2022 - 14:32 |
Event Stop | 14/09/2022 - 03:00 |
Unit of measurement | MW |
Unavailable capacity | 261 |
Available capacity |
140 |
Installed Capacity | 401 |
Reason for the unavailability | Failure on blower |
Remarks | UMM published on Nord Pool: https://umm.nordpoolgroup.com/#/messages/7892fb94-1ef0-450c-bed4-283d98ba817d/2 |
Fuel Type | Fossil hard coal |
Balancing zone | DK1 |
Affected Asset or Unit | ESV3 |
Affected Asset or Unit EIC code | 45W000000000040U |
Market Participant | Orsted Bioenergy Thermal Power A/S |
Market Participant Code | A00012832.DK |
Cancellation - Orsted AS Unplanned Outage ESV3
2022-09-13T21:33:00.0000000Z