WOW2 Wallney, 2012-09-05 17:16 CEST (GLOBE NEWSWIRE) --
| Reference number / Reference nummer | 20120905(MOGBE)-01 |
| Type of asset or agreement / Form for aktiv eller aftale | Wind |
| Affected unit(s) / Påvirket anlæg | Walney 2 |
| Country / Land | UK |
| Time of capacity reduction / Tidspunkt for reduktion i kapacitet | 25.sept to 28.sept 2012 at daytime |
| Company / Virksomhed | [Renewables] |
| Cause / Årsag | Maintenance / Vedligehold |
| Type of fuel(s) / Brændstof | Power |
| Capacity influenced / Påvirket kapacitet | 100% 183,6MW |
| Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold | The power is fluctuating during the test days. |
| Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold | approx 2 hours each day |
| Duration uncertainty / Usikkerhed | +/- 24 hours |
| Additional information / Yderligere information | INSERT DATA |
| Event status | INSERT DATA |