DONG Energy A/S - Severn 20 Made Available following delayed start due to ST Controller fault

 

General Template for Regulatory Reporting    
     
Reference number / Reference nummer 20120827RWJ-01   
Type of asset or agreement / Form for aktiv eller aftale Power Plant  
Affected unit(s) / Påvirket anlæg Severn 20  
Country / Land UK  
Time of capacity reduction / Tidspunkt for reduktion i kapacitet 21:00  
Company / Virksomhed Siemens O+M  
Cause / Årsag Steam turbine control fault  
Type of fuel(s) / Brændstof NG  
Capacity influenced / Påvirket kapacitet 400MW  
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold 0MW  
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold 03:40  
Duration uncertainty / Usikkerhed +/- 10 min  
Additional information / Yderligere information Faulty HP Pressure transmitter replaced. Unit made available from 21:00 on Monday August 27 2012.
Event status Active.  