Update: Orsted A/S – HOW01 - 3 - Planned frequency testing (UMM now posted on BMRS after down time)

Reference number 20201123 KRRAY-01
Type of asset or agreement Offshore Wind
Affected unit(s) HOW01 -3
Country United Kingdom
Time of capacity reduction 24-November-2020 08:00 GMT
Company Ørsted Wind Power A/S
Cause Planned Outage
Type of fuel Wind
Capacity influenced 400MW
Available capacity during outage or maintenance 0MW
Estimated outage or maintenance duration 24-November-2020 17:00 GMT
Additional information HOW01 – 3 will be undergoing frequency response testing. During this period the production will fluctuate between 400MW and 0MW. This UMM has now been posted on BMRS after a period of downtime. Please see below link to the current UMM on BMRS. https://www.bmreports.com/bmrs/?q=remit/11XDONG-PT-----2-NGET-RMT-00001016/1/DONG013