DONG Energy A/S - 16-Nov-2016 BKR01 reduced to 100MW on TernneT site

Event start:                 16.11.2016 12:54PM

Event stop:                         Time of Event start plus 1 minute

Available capacity:           [100] MW

Remarks:                            This is a non-operator REMIT market message.

 

An unplanned outage for [name of wind farm] has occurred as a consequence of an outage on a 3rd party asset restricting our access to the wider power network.

 

                                             This REMIT market message only contains information available to us at the time of publication. As we are not the operator of the asset causing the outage, further relevant information may exist and we will not be able to update this REMIT market message systematically.