DONG Energy A/S - 01.10.2016, 14:30 CEST REMIT Extended Gode Wind 1 & 2

 

Event start:                         01.10.2016 14:30 ces

Event stop:                         Time of Event start plus 1 minute

Available capacity:              0 MW

Remarks:                            This is a non-operator REMIT market message.

 

An unplanned outage for Gode Wind 1 & 2 has occurred as a consequence of an outage on a 3rd party asset restricting our access to the wider power network.

 

                                             This REMIT market message only contains information available to us at the time of publication. As we are not the operator of the asset causing the outage, further relevant information may exist and we will not be able to update this REMIT market message systematically.