DONG Energy A/S - Severn Unit 20 Unavailable from 00:00 27-07-2013 to 11:00 28-07-2013

Severn Power Station Newport UK, 2013-07-25 16:22 CEST (GLOBE NEWSWIRE) --  

Reference number / Reference nummer 20130725IKING-01
Type of asset or agreement / Form for aktiv eller aftale Power Plant
Affected unit(s) / Påvirket anlæg Severn 20
Country / Land UK
Time of capacity reduction / Tidspunkt for reduktion i kapacitet  27/07/2013 00:00
Company / Virksomhed DONG Naturgas A/S
Cause / Årsag Planned Maintenance / Vedligehold
Type of fuel(s) / Brændstof Power
Capacity influenced / Påvirket kapacitet 400 MW
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold Zero 
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold 35 Hours RTS 11:00 28/07/13
Duration uncertainty / Usikkerhed +/- 6 hours
Additional information / Yderligere information  Severn Power Unit 20 will be unavailable for 35 hours from 00:00 Saturday 27th July 2013 to 11:00 Sunday 28th July 2013 to carry out balancing adjustments to the GT.
Event status Confirmed
* Choose timezone CET: Central European Time or GMT: Greenwich Mean Time