DONG Energy A/S - Unit 20 decoupled and ready to be recoupled and loaded up to PN value

 

General Template for Regulatory Reporting   
   
Reference number / Reference nummer 2013/07/18RJ-02
Type of asset or agreement / Form for aktiv eller aftale Power Plant
Affected unit(s) / Påvirket anlæg Severn 20
Country / Land Wales UK
Time of capacity reduction / Tidspunkt for reduktion i kapacitet  10:00 to 12:00 GMT
Company / Virksomhed DONG Energy
Cause / Årsag Maintenance / Vedligehold
Type of fuel(s) / Brændstof Fuel Gas
Capacity influenced / Påvirket kapacitet 200 MW
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold 100MW
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold 2 hrs
Duration uncertainty / Usikkerhed +/- 30 min
Additional information / Yderligere information High shaft vibration in generator forcing decoupling of ST and recoupling
Event status INSERT DATA