Reference number | 20121207iking-02 |
Type of asset or agreement | Power Plant |
Affected unit(s) | Severn 10 |
Country | UK |
Time of capacity reduction | 11-01-2013 22:00 |
Company | DONG Naturgas A/S |
Cause | Planned Maintenance |
Type of fuel(s) | Gas |
Capacity influenced | Full outage / commissioning activity |
Available capacity during outage or maintenance | Zero - intermittent loading |
Estimated outage or maintenance duration | 18-03-2013 |
Duration uncertainty | +/- 7days |
Additional information |
Severn Power Station Unit 10 will have a planned outage from 11-1-2013 to 18-3-2013. In the time period from 25-2-2013 until the expected return to full commercial operation on 18-3-2013, there will be a test period and partial return to service. In this period the market should expect various levels of generation, subject to commissioning and testing progress. Should start of the outage or the return to full commercial operation be delayed or brought forward, DONG Energy will release a new market update with the new expected commercial operation dates. |
Event status | Confirmed |