2012-04-07T17:54:04.0000000Z
DONG Energy A/S - Unit 10 Available for Commercial Operation from 19:00 on April 19 2012
|
|
|
|
General Template for Regulatory Reporting |
|
|
|
|
|
Reference number / Reference nummer |
2012/04/07/RJ/01 |
|
Type of asset or agreement / Form for aktiv eller aftale |
Power Plant |
|
Affected unit(s) / Påvirket anlæg |
Severn 10 |
|
Country / Land |
UK |
|
Time of capacity reduction / Tidspunkt for reduktion i kapacitet |
19:00:00 Unit Available for Commercial Operation |
|
Company / Virksomhed |
DONG Energy |
|
Cause / Årsag |
Outage / Nedbrud |
|
Type of fuel(s) / Brændstof |
Natural Gas |
|
Capacity influenced / Påvirket kapacitet |
425 MW |
|
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold |
0MW |
|
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold |
19:00 Hours |
|
Duration uncertainty / Usikkerhed |
+/- 10 min |
|
Additional information / Yderligere information |
Unit 10 Available for Commercial Operation following IBO from 24:00 on April 6 2012. |
|
Event status |
open |
|