DONG Energy A/S - Severn Unit 10 Return to commercial operations

Severn Power Station Newport UK, 2013-03-08 17:11 CET (GLOBE NEWSWIRE) --  

Reference number / Reference nummer 20130308IKING-03
Type of asset or agreement / Form for aktiv eller aftale Power Plant
Affected unit(s) / Påvirket anlæg Severn 10
Country / Land UK 
Time of capacity reduction / Tidspunkt for reduktion i kapacitet  Ongoing
Company / Virksomhed DONG Naturgas A/S
Cause / Årsag Planned Maintenance / Vedligehold
Type of fuel(s) / Brændstof Power
Capacity influenced / Påvirket kapacitet Full outage / commissioning activity
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold Zero 
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold 13/03/2013
Duration uncertainty / Usikkerhed +/- More than 1 day
Additional information / Yderligere information This is a general service notice update that Severn Power Station Unit 10  planned outage from 18/01/2013 is expected to return to full commercial operation at 06:00 on 13/03/2013.
In the time frame from first fire on 26/02/2013 until the expected return to full commercial operation on 13/03/2013, there will be a test period and partial return to service. In this period the market should expect various levels of generation, subject to commissioning and testing progress.

Should the return to full commercial operation be delayed or brought forward, DONG Energy will release a new market update with the new expected commercial operation dates.
Event status Confirmed
* Choose timezone CET: Central European Time or GMT: Greenwich Mean Time