DONG Energy A/S - 22-aug-2012 Walney 1 - Compliance test - Substation

 

Reference number / Reference nummer 20120820STMAR-01
Type of asset or agreement / Form for aktiv eller aftale Wind 
Affected unit(s) / Påvirket anlæg Walney 1
Country / Land UK
Time of capacity reduction / Tidspunkt for reduktion i kapacitet  22-aug-2012 09:00 GMT
Company / Virksomhed [Renewables]
Cause / Årsag Compliance test - Substation
Type of fuel(s) / Brændstof Power
Capacity influenced / Påvirket kapacitet 184 MW
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold I0 MW
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold 22-aug-2012 18:00 GMT
Duration uncertainty / Usikkerhed +/- 1 hour
Additional information / Yderligere information Fluctuating production
Event status Open
Reference number / Reference nummer 20120820STMAR-01
Type of asset or agreement / Form for aktiv eller aftale Wind 
Affected unit(s) / Påvirket anlæg Walney 1
Country / Land UK
Time of capacity reduction / Tidspunkt for reduktion i kapacitet  22-aug-2012 09:00 GMT
Company / Virksomhed [Renewables]
Cause / Årsag Compliance test - Substation
Type of fuel(s) / Brændstof Power
Capacity influenced / Påvirket kapacitet 184 MW
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold I0 MW
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold 22-aug-2012 18:00 GMT
Duration uncertainty / Usikkerhed +/- 1 hour
Additional information / Yderligere information Fluctuating production
Event status Open