seven power south wales uk, 2013-11-04 02:00 CET (GLOBE NEWSWIRE) --
Reference number / Reference nummer | 2013.11.04[initialer]-02 |
Type of asset or agreement / Form for aktiv eller aftale | Power Plant |
Affected unit(s) / Påvirket anlæg | Severn unit 20 |
Country / Land | Wales |
Time of capacity reduction / Tidspunkt for reduktion i kapacitet | none |
Company / Virksomhed | Dong Energy |
Cause / Årsag | GT compressor wash |
Type of fuel(s) / Brændstof | Gas |
Capacity influenced / Påvirket kapacitet | 410MW |
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold | 0 mw |
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold | 2 hrs |
Duration uncertainty / Usikkerhed | +/- 30 min |
Additional information / Yderligere information | unit 20 GT off line wash completed unit 20 availiable |
Event status | unit availiable from 01.00 GMT |