2013-09-24T14:47:54.0000000Z
DONG Energy A/S - Severn Power Unit 10 shutdown from September 26 (23:00 GMT) to September 30 (02:00 GMT)
|
General Template for Regulatory Reporting |
|
|
|
|
|
Reference number / Reference nummer |
2013/09/24 RWJ (01) |
|
Type of asset or agreement / Form for aktiv eller aftale |
Power Plant |
|
Affected unit(s) / Påvirket anlæg |
Severn 10 |
|
Country / Land |
Wales UK |
|
Time of capacity reduction / Tidspunkt for reduktion i kapacitet |
September 26 (23:00 GMT) to September 30 (02:00 GMT) |
|
Company / Virksomhed |
DONG Energy |
|
Cause / Årsag |
Maintenance / Vedligehold |
|
Type of fuel(s) / Brændstof |
Natural Gas |
|
Capacity influenced / Påvirket kapacitet |
415 MW |
|
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold |
0 MW |
|
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold |
75 hours |
|
Duration uncertainty / Usikkerhed |
+/- 1 hour |
|
Additional information / Yderligere information |
Repairs to flexible joint on GT exhaust |
|
Event status |
No |
|