DONG Energy A/S - Severn Unit 10 delayed start due to problems with the GT turning gear

 

General Template for Regulatory Reporting   
   
Reference number / Reference nummer 2013-07-22 RJ-01
Type of asset or agreement / Form for aktiv eller aftale Power Plant
Affected unit(s) / Påvirket anlæg Severn 10
Country / Land Wales Uk
Time of capacity reduction / Tidspunkt for reduktion i kapacitet  12:00 GMT July 22 2013
Company / Virksomhed DONG Energy
Cause / Årsag Maintenance / Vedligehold
Type of fuel(s) / Brændstof Fuel Gas
Capacity influenced / Påvirket kapacitet 400 MW
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold 0 MW
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold 4 hours - Extending Outage Time from 08:00 GMT to 12:00 GMT on July 22 2013
Duration uncertainty / Usikkerhed +/- 30 min
Additional information / Yderligere information Due to ongoing problems with GT turning gear
Event status INSERT DATA