DONG Energy A/S - Severn Power Unit 10 Minor Outage

 

General Template for Regulatory Reporting   
   
Reference number / Reference nummer 2013/07/11RJ-01
Type of asset or agreement / Form for aktiv eller aftale Power Plant
Affected unit(s) / Påvirket anlæg Severn 10
Country / Land Wales UK
Time of capacity reduction / Tidspunkt for reduktion i kapacitet  120 hr
Company / Virksomhed DONG Energy
Cause / Årsag Outage / Nedbrud
Type of fuel(s) / Brændstof Natural Gas
Capacity influenced / Påvirket kapacitet 420 MW
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold 0
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold 120 hr
Duration uncertainty / Usikkerhed +/- 12 hours
Additional information / Yderligere information Outage period commence on July 16 2013 at 23:00 hrs (GMT).
Event status INSERT DATA
* Choose timezone CET: Central European Time or GMT: Greenwich Mean Time