DONG Energy A/S - Severn Power Unit 20 Unavailable for 48 hours from 23.00 28th June

Severn Power Station Newport UK, 2013-06-27 14:08 CEST (GLOBE NEWSWIRE) --  

Reference number  20130627IKING-01
Type of asset or agreement  Power Plant
Affected unit(s)  Severn 20
Country UK
Time of capacity reduction 28/06/2013 23:00
Company DONG Naturgas A/S
Cause Planned Maintenance
Type of fuel(s)  Power 
Capacity influenced 400 MW
Available capacity during outage or maintenance Zero
Estimated outage or maintenance duration 48 Hours
Duration uncertainty +/- 6 hours
Additional information  This is an update notification that the planned unavailability of Severn Unit 20 is delayed by 1 hour. Severn Power Unit 20 will be out of service between 23:00 on Friday 28th June 2013 until 23:00 Sunday 30th June 2013 due to planned repairs to the HP Bypass valve
Event status Confirmed