DONG Energy A/S - Severn Power Unit 20 unavailable for 9 hours from 20.00 11th June 2013

Severn Power Station Newport UK, 2013-06-10 17:23 CEST (GLOBE NEWSWIRE) --  

Reference number / Reference nummer 20130610IKING-01
Type of asset or agreement / Form for aktiv eller aftale Power Plant
Affected unit(s) / Påvirket anlæg Severn 20
Country / Land UK
Time of capacity reduction / Tidspunkt for reduktion i kapacitet  11/06/2013 20:00
Company / Virksomhed DONG Naturgas A/S
Cause / Årsag Planned Maintenance / Vedligehold
Type of fuel(s) / Brændstof Power
Capacity influenced / Påvirket kapacitet 400 MW
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold Zero 
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold 9 Hours RTS 05:00 12/6/13
Duration uncertainty / Usikkerhed +/- 1 hour
Additional information / Yderligere information  Severn Power Unit 20 will be unavailable for 9 hours from 20:00 Tuesday 11th June 2013 to 05:00 Wednesday 12th May 2013 to carry out Set-up checks and adjustments to the HP by-pass steam valve.
Event status Confirmed