Severn Power Station Newport UK, 2013-06-10 17:23 CEST (GLOBE NEWSWIRE) --
Reference number / Reference nummer | 20130610IKING-01 |
Type of asset or agreement / Form for aktiv eller aftale | Power Plant |
Affected unit(s) / Påvirket anlæg | Severn 20 |
Country / Land | UK |
Time of capacity reduction / Tidspunkt for reduktion i kapacitet | 11/06/2013 20:00 |
Company / Virksomhed | DONG Naturgas A/S |
Cause / Årsag | Planned Maintenance / Vedligehold |
Type of fuel(s) / Brændstof | Power |
Capacity influenced / Påvirket kapacitet | 400 MW |
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold | Zero |
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold | 9 Hours RTS 05:00 12/6/13 |
Duration uncertainty / Usikkerhed | +/- 1 hour |
Additional information / Yderligere information | Severn Power Unit 20 will be unavailable for 9 hours from 20:00 Tuesday 11th June 2013 to 05:00 Wednesday 12th May 2013 to carry out Set-up checks and adjustments to the HP by-pass steam valve. |
Event status | Confirmed |
* Choose timezone CET: Central European Time or GMT: Greenwich Mean Time |