Severn Power Station Newport UK, 2013-05-21 15:25 CEST (GLOBE NEWSWIRE) --
Reference number / Reference nummer | 20130521IKING-01 |
Type of asset or agreement / Form for aktiv eller aftale | Power Plant |
Affected unit(s) / Påvirket anlæg | Severn 20 |
Country / Land | UK |
Time of capacity reduction / Tidspunkt for reduktion i kapacitet | 24/05/2013 22:00 |
Company / Virksomhed | DONG Naturgas A/S |
Cause / Årsag | Planned Maintenance / Vedligehold |
Type of fuel(s) / Brændstof | Power |
Capacity influenced / Påvirket kapacitet | 400 MW |
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold | Zero |
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold | 54 Hours RTS 04:00 27/5/13 |
Duration uncertainty / Usikkerhed | +/- 1 hour |
Additional information / Yderligere information | This is an update message that Severn Power Unit 20 will be unavailable for 54 hours from 22:00 Friday 24th May 2013 to 04:00 Monday 27th May 2013 to carry out repairs to a leaking steam valve. |
Event status | Confirmed |