Severn Power Newport, 2013-05-08 12:02 CEST (GLOBE NEWSWIRE) --
| Template for Regulatory Reporting SEVERN | ||
| Reference number / Reference nummer | 08/05/2013 | |
| Affected unit(s) / Påvirket anlæg | Severn | |
| Affected market / Påvirket marked | UK Power | |
| Time of capacity reduction / Tidspunkt for reduktion i kapacitet | 08/05/13 09:00 | |
| Company / Virksomhed | DONG Naturgas A/S | |
| Type of asset or agreement / Form for aktiv eller aftale | Power Plant | |
| Cause / Årsag | Faulty ESV valve on ST10 | |
| Type of fuel(s) / Brændstof | Gas | |
| Capacity influenced / Påvirket kapacitet | 140 MW | |
| Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold | 280 MW (single cycle only) | |
| Estimated time of outage or maintenance / Vurderet varighed for nedbrud eller vedligehold | 09/05/2013 06:00 | |
| Duration uncertainty / Usikkerhed | 3 hours | |
| Additional information / Yderligere information | ST Unit 10 not available until faulty ESV repoaired. | |
| * Choose timezone: Central European Time (CET) or Greenwich Mean Time (GMT) | ||