2012-11-02T08:45:15.0000000Z
DONG Energy A/S - 02-nov-2012 Walney 1 out due to transformertrip at Heysham
|
Reference number / Reference nummer |
20121102PETJE01 |
|
Type of asset or agreement / Form for aktiv eller aftale |
WIND |
|
Affected unit(s) / Påvirket anlæg |
Walney 1 |
|
Country / Land |
UK |
|
Time of capacity reduction / Tidspunkt for reduktion i kapacitet |
02-NOV-2012 08:10 GMT |
|
Company / Virksomhed |
DONG Wind Power |
|
Cause / Årsag |
Outage / Nedbrud |
|
Type of fuel(s) / Brændstof |
Power |
|
Capacity influenced / Påvirket kapacitet |
184 MW |
|
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold |
0 MW |
|
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold |
31 hours |
|
Duration uncertainty / Usikkerhed |
+/- 1 hour/time |
|
Additional information / Yderligere information |
132Kv switchgear trip on the offshore platform |
|
Event status |
Closed |