Reference number / Reference nummer | 20121015(lrasm)-01 |
Type of asset or agreement / Form for aktiv eller aftale | WIND |
Affected unit(s) / Påvirket anlæg | Gunfleet sands 1&2 |
Country / Land | UK |
Time of capacity reduction / Tidspunkt for reduktion i kapacitet | 15-October-2012 00:20 GMT |
Company / Virksomhed | DONG Wind Power |
Cause / Årsag | Outage / Nedbrud |
Type of fuel(s) / Brændstof | Power |
Capacity influenced / Påvirket kapacitet | 172 MW |
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold | 0 MW |
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold | End date/slutdato: 15-October-2012 |
Duration uncertainty / Usikkerhed | +/- 12 hours/timer |
Additional information / Yderligere information | Substation has tripped |
Event status | Open |