London Array, 2012-09-28 15:12 CEST (GLOBE NEWSWIRE) --
Wind Power Template for Regulatory Reporting | ||
Reference number / Reference nummer | 20120928LONER-01 | |
Type of asset or agreement / Form for aktiv eller aftale | WIND | |
Affected unit(s) / Påvirket anlæg | London Array | |
Country / Land | UK | |
Time of capacity reduction / Tidspunkt for reduktion i kapacitet | 22-10-2012 hour 12:00 GMT | |
Company / Virksomhed | DONG Wind Power | |
Cause / Årsag | Under construction | |
Type of fuel(s) / Brændstof | Power | |
Capacity influenced / Påvirket kapacitet | 630 MW | |
Lowest available capacity during outage or maintenance / Lavest kapacitet til rådighed under nedbrud el.vedligehold | 0 MW | |
Estimated duration / Vurderet varighed | End date/slutdato: 31-03-2013 hour 12:00 GMT | |
Duration uncertainty / Usikkerhed | +/- 8-31 days | |
Additional information / Yderligere information | London Array Offshore Wind Farm is under construction and wind turbines will be successively connected to the grid. Expected date for the first connection is on 22 October 2012, and all wind turbine connections finalised by March 2013. During and subsequent to this period there will be tests of unknown length where effect will vary. Duration Uncertainty the relates to the unknown length of the test period hence the final commissioning date. | |
Event status | Open |