Severn Power Unit 20 Minor Inspection Outage is currently scheduled for 5 days from approximately 1st August 2012.
General Template for Regulatory Reporting | |
Reference number / Reference nummer | 20120314-01 |
Type of asset or agreement / Form for aktiv eller aftale | Power Plant |
Affected unit(s) / Påvirket anlæg | Severn 20 |
Country / Land | UK |
Time of capacity reduction / Tidspunkt for reduktion i kapacitet | 1st August 2012 |
Company / Virksomhed | DONG Naturgas A/S |
Cause / Årsag | Planned Maintenance / Vedligehold |
Type of fuel(s) / Brændstof | Power |
Capacity influenced / Påvirket kapacitet | 405MW |
Available capacity during outage or maintenance / Kapaciett til rådighed under nedbrud el.vedligehold | 0MW |
Estimated outage or maintenance duration / Vurderet varighed for nedbrud eller vedligehold | 5th August 2012 |
Duration uncertainty / Usikkerhed | +/- 12 hours |
Additional information / Yderligere information | |
Event status | |